Skip to Content

SAP_MULT_SCH not working

Sep 07, 2017 at 01:28 AM


avatar image

Hi ,

Heuristics - SAP_MULT_SCH , resulting in error - "Heuristics executed without result".

The clarification needed is , does this work for "Alternate resources" , or only " Alternate modes of the same resources".

Based on Wiki - ,

It should work on alternate resources , ReS A is overloaded on the particular date , but Res B is not chosen automatically by the Heuristics.

Priority - maintained in the PDS for both the resources - accordingly ,

Help on this is appreciated. Thanks


10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

0 Answers