Hi,

Can anyone tell me, as I am not getting the planned cost in any report for any WBS element for which I have entered the manual planned cost using CJ40. what are the settings that has to be made in IMG for getting that, as i have the maintained the planning profile for the hierarcical cost planning.Kindly advise.

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

1 Answer

  • Best Answer
    author's profile photo
    Former Member
    Posted on Sep 28, 2007 at 06:03 PM

    Hi,

    The planned cost can be obtained in report such as CN41/CNS41/CN41N etc. Please check the planning profile & assignment of that to project profile. Please check the costing variants also.

    Hope this will help you.

    Regards,

    Rakesh Pradhan

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Thanks forthe response Mr. Pradhan,

      I have checked with the planning profile for the hierarcical planning( I have selected the planning element check box in planning profile and in costing variant of the unit costing, for the valuation variant for activity type/ process I have selected the priorty as Plann price as an average of all fiscal year.

      regards