on 09-28-2007 4:41 PM
Hi,
Can anyone tell me, as I am not getting the planned cost in any report for any WBS element for which I have entered the manual planned cost using CJ40. what are the settings that has to be made in IMG for getting that, as i have the maintained the planning profile for the hierarcical cost planning.Kindly advise.
Hi,
The planned cost can be obtained in report such as CN41/CNS41/CN41N etc. Please check the planning profile & assignment of that to project profile. Please check the costing variants also.
Hope this will help you.
Regards,
Rakesh Pradhan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks forthe response Mr. Pradhan,
I have checked with the planning profile for the hierarcical planning( I have selected the planning element check box in planning profile and in costing variant of the unit costing, for the valuation variant for activity type/ process I have selected the priorty as Plann price as an average of all fiscal year.
regards
Avisek
User | Count |
---|---|
99 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.