Dear All,
Please suggest in case of my following scenario:
If I want to measure the project progress on the basis of work completed on each activities under several wbs and then total of project under which these WBS come.
I am using progress version with basis as Work. Assigning Degree of completion as measuring method to actual method in Progress Tab of each activity(Both Internal and external).
In CNE5 i get the correct % of work and weight for each activity.
But when I assign weight to the WBS above these activities and suppose there are three parallel WBS like this then I canot access the work done for each WBS.
As SAP does not allow % of work done for WBS.
Can somebody suggest something please.
Thanks in advance
Regards
Maneesh