factory calendor

what is the relavance of factorycalendor

please reply me

thanku

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

3 Answers

  • Best Answer
    author's profile photo
    Former Member
    Posted on Sep 28, 2007 at 09:10 AM

    Factory calendar contain company specific dates such as alternate working Saturdays, Plant shutdown etc.

    You can create your company factory calendar via transaction code 'SCAL'.

    Assignment of the factory calendar by plant is done in transaction code 'SM30 - V_T001W'.

    An example of a SAP application that uses the factory calendar is the SAP MRP modules.

    Assuming that you have a specified an alternate working Saturday, MRP will postponed the planned orders to the next working day if it happened to falls on a non-working Saturday.

    Add comment
    10|10000 characters needed characters exceeded

  • author's profile photo
    Former Member
    Posted on Sep 28, 2007 at 08:32 AM

    hi

    factory calendar plays a vital role in SAP .the effects of the calendar is very helpful .

    here when we create ,purchase,deliver,receive we check out for a date here when we receive something or issue something system consider the dates these days are working days,where if we want to procure material on holiday i.e date system gives you a warning or error (depends) and automatically consider the next working date

    Go SAP Customizing Implementation Guide -->SAP NetWeaver -->General Settings -->Maintain Calendar OR type T code as --> SCAL

    01>Select Public Holidays : Click create / change

    Here you can create your holidays ( select fixed or floating holidays,based on requirement)

    02 > Create a Holiday calendar : Enter ID and description, Incorporate the holidays creates above

    03 > Create Factory calendar : Enter ID and description, From year to TO year, Holiday calender, Factory data start , working days

    and SAVE

    Now assign this to Plant under

    Enterprise Structure >Definition>Logistics - General-->Define, copy, delete, check plant

    Add comment
    10|10000 characters needed characters exceeded

  • author's profile photo
    Former Member
    Posted on Sep 28, 2007 at 08:32 AM

    Factory calendar contain company specific dates such as alternate working Saturdays, Plant shutdown etc.

    You can create your company factory calendar via transaction code 'SCAL'.

    Always attached to a plant 'ox10'

    An example of a SAP application that uses the factory calendar is the SAP MRP modules. Assuming that you have a specified an alternate working Saturday, MRP will postponed the planned orders to the next working day if it happened to falls on a non-working Saturday.

    <b>Rajesh</b>

    Do Reward if useful..