Time required to make assembly??

Former Member
0 Kudos

Hi

Is there any direct link or setting available from where i can view that it takes 3 days or 35 hours or whatever (for example) to produce 10 or 20 (for example) components???

I mean to say that how will a new user come to know that how much time will it take to make components based on my work center capacity and setting made in routing & schedule orders at shop floor for production????

Please give your valuable comments with an example.....and get rewarded

Rgds

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Vicky,

setting we do in Master data and when we ran MRP it takes all master data and process the date and consider the capacity

you can check in Planned order how capacity is used for that material

another one is in Work center also we have check of formula where you can check how much hr it takes to produce number of qntys

Cheers

Bala

Former Member
0 Kudos

Hi

By scheduling the routing you can know this.

In the operation over view screen in routing you follow the menu

Extras>scheduling>schedule

there you input your required qty then you will get the scheduling over view.

Then select the button scheduling results.

Then you will get the required result.

Pl. award if you get the solution.Other wise update the thread.

Regards

YMREDDY