Routing

Can any body tell me how is the scheduling carried with respect to Routing and the capacity mentioned in routing.

In my scenerio I have maintained 25 Work Centers and my raw material passes thru all the WC's and in my routing I have given That It can produce the total quantity as per the capacity in my WC.

Eg:

Wc Capacity : 18 hrs

in Routing : fro each WC only M/C time and labour time is there

Here I have mentioned both take 18hrs to produce 100pcs.

Is it ok or I have to do it some other way

Regards

Suresh

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

1 Answer

  • author's profile photo
    Former Member
    Posted on Sep 28, 2007 at 07:09 AM

    Hi Suresh,

    all 25 WC you need to mention in operation and goto each operation and give m?C time and base qnty which is impt.

    for ex WC m/C time is 1 hr and in one hr 50 pc can be produced

    then give 50pc base qnty and m/C time is 1 hr , system will calculate based on formula you have maintioned in WC

    Cheers

    Bala