hi,

While upgrading Support Pack on XI system, Is there any sequence that i need follow like ABAP first then JAVA or vise versa......Please suggest and also give me refence if any for more information regarding same.

Thanks

Sekhar

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

1 Answer

  • author's profile photo
    Former Member
    Posted on Sep 28, 2007 at 07:15 AM

    Hi,

    I just upgraded XI 7.0 from SP9 to SP12.

    I did first ABAP then JAVA with JSPM. It worked perfectly !

    It took me around 6 hours.

    Regards,

    Olivier