Scheduling & capacity

Hi All,

When I am creating production order and scheduling it for the day. I have config. For Forward scheduling I have said in my routing the time taken for producing 100pcs it takes another three days for the completion of the order but it is taking 4 days to complete the order instead of the same day. Can anybody help where I have missed.

Regards

Suresh

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

4 Answers

  • author's profile photo
    Former Member
    Posted on Sep 28, 2007 at 06:06 AM

    Hi suresh,

    please check with Avilable capacity of your work center. Have you taken the account of Avilable capacity time while giving the time to routing...

    regards

    pradeep

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi

      It is happening for all my orders. I have checked with my WC capacities Here too the capacity is for 18 HRS my shift schedule is for 24 hrs but still I am facing the same problem.

      Regards

      Suresh

  • author's profile photo
    Former Member
    Posted on Sep 28, 2007 at 06:09 AM

    Is this happening for this particular order or even other orders are behaving like this???

    Rgds

    Add comment
    10|10000 characters needed characters exceeded

  • author's profile photo
    Former Member
    Posted on Sep 28, 2007 at 06:14 AM

    go to the operation details of the Production order and find out the Operation schedule dates, it will give you some idea.

    Add comment
    10|10000 characters needed characters exceeded

  • author's profile photo
    Former Member
    Posted on Sep 28, 2007 at 06:14 AM

    Hi,

    Have u checked the Schedule Margin Key? - ( Check the no. of days in Float before production and float after production )

    - Thaila Shree

    Add comment
    10|10000 characters needed characters exceeded