Hello experts. I am having some trouble with the schedule lines in our sales orders. There used to be only one schedule line with the requested qty and the confirmed qty. But ever since I configured the factory calender in our shipping poitns, there have been appearing two shipping lines. The first one, with today's delivery date and the requested quantity. The second one with the confirmed quantity and a delivery date a few days in the future. Does anyone know how I can configure so that the shipping lines stay on one line, with today's delivery date?

Here are links to print screens of what is happening:

http://img441.imageshack.us/img441/9159/delivery1eu5.jpg

http://img118.imageshack.us/img118/1561/delivery2ho7.jpg

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Edson,

I believe this is a result of your availability check. Now that you have maintained the factory calendars, the lead time takes into account free days vs. working days maintained in the factory calendar.

Example: today's date is 9/27 and your lead time is 5 days

Before you maintained the factory calendars, SAP was assuming all calendar days are working days. Therefore, an order with RDD of 10/2 would be confirmed.

Now let's say you maintain the factory calendar with the weekends free. 5 working days from the 27th is 10/4. Your order will no longer be confirmed unless you change the RDD to 10/4.

Hope this helps,

Rob

Former Member
0 Kudos

Robert, you seem to be on right track. I checked the availability and that's whats creating the second schedule line. For some reason, when I have the calendar maintained in the shipping point, it makes the goods only available 2 days in the future, even though I have plenty of it in stock ready to be shipped. Do you know where that "lead time" is configured?

Answers (3)

Answers (3)

Former Member
0 Kudos

hi,

kindly check the simple steps to overcome of your error.

1. in your plant and shipping point what the factory calendar is maintained?

2. see the invoice date calendar under shipping tab in your customer master.

regards

KR

Lakshmipathi
Active Contributor
0 Kudos

Hi Edson

Please check in OVLZ, select your shipping point and see any numeric is entered in "Pick/pack time wrkdys". For example, if 5 is given in this field, even if stock is available on the day of sale order creation, only after 5 days, you can make a delivery.

Confirm please if this solves your problem.

Thanks

G. Lakshmipathi

dilip_choudhury
Active Participant
0 Kudos

Hi

I think you need to maintain customer master ( Sales area data ) in shipping tab ,Partial delivery field to be as B .This create one delivery .

Hope this will fix this issue

Dilip

Former Member
0 Kudos

Thanks for your response Dilip, but unfortunatelly that didn't solve the problem