Hello,

I am using CM21 for capacity leveling.

I have blocked workcenter capacity for some period (say for 8 hrs), the issue is when I select the operation and dispatch using dispatch button (F5 key) system is dispatching operation in blocked period without any error or warning. and When I manually drag and drop the operation from orders pool on blocked period I get moved ahead at the end of blocked period automatically which is correct behavior.

So I want the operation should not be dispatched in blocked period when I dispatch it using DISPATCH button (F5).

As you can see operation is dispatched on 07:00 Hrs which is blocked, I want it should be dispatched automatically to 15 Hrs where capacity is available.