How to transfer back the cost from cost center to production order

Hi,

We have done settlement from production order to material and the corresponding cost centre is updated with cost. After when we reverse the settlement, actual got transferred to production order but still we have a balance in cost center due to change in Moving average price in material master. How to remove the additional cost in cost center??

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

1 Answer

  • Posted on Sep 08, 2017 at 02:35 PM

    KB61 - Reposting Line items -> to Keep the cost element but to change the account assignment

    FB01 - Post FI doc -> change account assignment and cost element.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.