PS/Internal Activity:- Work Centre to have unit of Measure other than time say EA.
I wish to use EA as UOM in WCentre of Internal Act. When I put EA I get this message:-
"Enter a time unit, since you have entered either work or actual workIn wormk"
Current settings are in WC:-
Basic Data Tab:-W.C. Categ:- 0006,
Cap Categ- 001, other form -SAP008 and 002, SAP 008,
Scheduling TAb:-WOrk Dimension - No dim., and Work Unit- EA
In Capacity detail also I ahve given 700 units = 9 hr of work
Standard av. Cap = 08.00.00 to 17.00.00
Thanks