Consignment Schedule Agreement

When a Consignment Schedule Agreement (CSA) is raised, and the material master special procurement key (SPK) is blank. System still generates CSA and no message is given to buyers that CSA is not in line with Material Master giving problem in planning.

How do I solve this query?

Thanks / Bhavesh

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Sep 25, 2007 at 02:34 PM

    Please check weather you have used item category "K" in Scheduling agreement or vendor you are using with consignment info type.

    regards

    venkadesh

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Sep 26, 2007 at 01:19 PM

    Thanks Venkadesh for the help.

    I could solve this query.

    Regards,

    Bhavesh

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.