Hi,
Is it possible to create some approval scenario for a task in cProject.
There are some tasks which need cost approval. Can anyone recommend an easy to implement solution using the standard by either reusing approval document or attaching a BW report with a task.
kind regds
Vishal
Dear Vishal,
the approval process is specific to (and exclusively implemented for) phases. Tasks and phases are different entities on a rather fundamental level and without heavy modifications approvals for tasks cannot be realised - if possible at all.
Best regards,
Thomas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Thomas,
I do understand and agree with your opinion. The issue is that we need to get an object approved that is not a phase in the main project definition. So just wondering if we can create this object as a phase under a subproject definition - This is just to avoid these huge modifications. So if we can treat a task as a phase of the subproject and trigger the approval of this, do you see any issues technically ? (Though there are issues in functional design, but they would outnumber the benefits if it can be realised ?)
Cheers
Vishal
Dear Vishal
You can certainly <b>treat a task as a phase</b> of the subproject and trigger the approval of this.
There is no problem for this
what u can do is
define a task have subproject attached to it and you are thru,
the subproject ll have a phase for which you can have approval process.
Regards,
Niranjan
Award if useful