One alternative would be:
- Customer material (CM) are non valuated ones.
- BoM contains both CM and normal raw materials (CS01)
- Routing ot Recipes is the base for manufacturing costing (CA01 or C201).
- Create a process order for the product (COR1)
- Do the whole processing of the order (release, GI, GR, Confirmation, Settlement).
-.Delivery the product to the customer (and eventually the remaining CM )
The process is just like the normal, only there are some differences in costing, and the stock of CM has no value.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
That would be dependent on the way you want to manage the receipt, but, as there is no value involved you could create a Purchase Order and do the GR for this order or making the receipt w/o Purchase Order or a mvmt type 501 or ...
That should not be the problem, but if I can get a better solution I will tell you
Regards
Hello, Sankaran
in the scenario I am working with, GR from customer materials are done by MIGO with Mvm type 511 ( no purchase order ).
However, in you want to use a PO, I guess that no problem about costing should arise.
The material type should be Non valuated and that define the way in which MM Costing view has to be completed.
Regards
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.