KO01 Internal Order table, planning

Hello, everyone

I was looking for the table, data element, in which the Internal KO01 Plan for SAP was written. Planned through KEP6. As for the actual costs, I can find their value in the COEP table linked to the object number, but only for the actual part (4).

Thank you for any reply

Emilio C

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Sep 01, 2017 at 09:22 PM

    CO Planning data (Cost Center, internal orders, wbs a.s.o.) is stored as follows:

    if Line-items are activated you find them in the table COEJ and following.

    The totals can be found in COSP (Primary) and COSS (secondary) value type 01.

    Regards

    Holger Homann