Can I modify GLUZP and GSUZP in a Order created by a Maintenance Plan?

Hi Experts,

I have a question, i created a Maintenance Plan that creates work orders every day. Every order has the GLUZP in 00:00 and the GSUZP in 00:00 , I want to change that. I need to configure the Maintenance Plan to create Orders with a particular starting hour and ending hour, but i dont know how.

Can anybody help me please?

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    Sep 04, 2017 at 08:58 AM

    Hi Alan,

    Is the time not updated based on your Task list ?

    Regards

    Terence

    Add comment
    10|10000 characters needed characters exceeded

    • Hi Alan,

      You can use the Task List to enter the hours required for your work. Scheduling of Time and date will happen based on the Work Center you have assigned by calculating the hours in the operation.

      Regards

      Terence

  • Sep 05, 2017 at 07:17 AM

    GLUZP - Basic start time

    GLUZP - Basic finish (time)

    Also, check the start/end times in the work centre.

    PeteA