table for Components in task list?

Sep 06, 2017 at 10:08 AM

38

avatar image
Former Member

Team,

How to find the logic for components assigned to a particular task list. Gone through the posts with STPO... but quantity not updating every time it is showing quantity as 1 only.

Regards,

Bhanu.

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Peter Atkin Sep 06, 2017 at 10:47 AM
1

Here's the logical database view of task lists (see transaction SE36 and PNI)

PLMZ is th table that holds tha material assignments to task ist operations

PeteA