Sub contracting PO " No Components Can Be Determined"

40 Views

Dear Peers,

While creating sub contracting PO, system throws message " Not possible to determine any component".

I maintained the BOM for the component & delivery dates are also in the specified date. Account assignment is "N" Networks

PR is created from Project systems under network

Can any one just point out the odd

Regards,

ProjectMan