Sub contracting PO " No Components Can Be Determined"

Dear Peers,

While creating sub contracting PO, system throws message " Not possible to determine any component".

I maintained the BOM for the component & delivery dates are also in the specified date. Account assignment is "N" Networks

PR is created from Project systems under network

Can any one just point out the odd

Regards,

ProjectMan

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Sep 21, 2007 at 04:26 PM

    hello,

    in cs03 see the bill of material is maintained or not.If no please maintained in cs01.

    I do see any other reason for this.

    Regards

    kedar

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Sep 21, 2007 at 04:29 PM

    Also check the material master for the purchased(parent item) to see if it is correclty flagged for external procuremnt and Sp.proc key for subcontracting in the MRP2 view.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.