PO without Costing

Hi experts,

recently i have this problem,

We have 2 new members, one reponsible in production order and another responsible in

production line.

First member create production order without costing, release , save and then send p/o to production.

Second member use MB31 good recieve from that p/o without cost.

How can i prevent this type of problem? Can i change warning message to error message? If possible how and where i should config?

i will give point for useful answer for sure.

regards.

Add a comment
10|10000 characters needed characters exceeded

Related questions

4 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Sep 21, 2007 at 12:23 PM

    Hi Kitti

    make it error msg

    Thanks

    Bala

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Sep 21, 2007 at 12:27 PM

    I donot think it is possible to do a GI/GR without the ordder status REL. Std SAP doesnot allow this.

    PLease confirm my understanding.

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi,

      OPL8-- Order type dependent parameters assign the costing varinats for the planning and actual costing varinats.

      Maintain 1 0r 2in the Plannined cost calculation field.

      this will make sute that the order is released with costing.

      I think once this is costed you will have any issues even if the goods movement is done for the production order,

      Reward if you like.

  • author's profile photo Former Member
    Former Member
    Posted on Sep 21, 2007 at 12:59 PM

    Dear,

    From your question What I understood is you want the costing to be automatic during release of the production order so that before you GR, the cost is calculated.

    if so,

    Do the following,

    in OPL8

    for the given order type and plant

    in controlling tab,

    planned cost calculation = 2(detremin planned cost when saving if released.)

    save it.

    it will work,

    if my understanding is wrong, pl come back

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Sep 21, 2007 at 01:07 PM

    Hi Hittisak,

    In OPL8- Order type dependent paramters go to controlling tab and select "Do not calculate planned cost when saving" in the planned cost calculation field.

    Then the order is not costed. Hope it solve your purpose. Kindly revert back if you need more information.

    Thanks and regards

    Murugean

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.