Hi Friends,

My client is using Abap list based PI sheets, where the process Instruction categories are getting copied from the configuration O10C (PI characteristics assigned to control recipe destination CRD ). its working in current plant with out any issue.

We have created a new plant for a roll out with exactly same functionality, where copied current plant. So all settings of Process management are exactly same. But when I am testing, the Process Instructions assigned to CRD is not getting copied to Process order.

Please suggest to fix this issue.