stock transport order ?

hi all,

in performing STO there are two methods

1.one step

2.two step

--->what & when is the rationale for using these two methods ?

-


>when does the company uses

1.sto w/o sd delivery

2.sto with sd delivery

any real time scenarios if possible ?

kindly do not copy & paste STO notes i have enough,kindly be precise .

thank you.

sriram.

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Sep 21, 2007 at 06:49 AM
    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Sep 21, 2007 at 09:33 AM

    Hi,

    There are two steps STO's and One step STO's.

    If you bring in the material through Material management without the relevence of SD , they do it with one step.

    If SD is involved and it is billing relevent the two step procedure will be followed. This is a very simple answer. But the concept ot these are really wide.

    Prase

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.