on 10-17-2016 1:37 AM
Hi Experts,
I have unrestricted storage location stock with shelf life expiration date on the 20.10.2016. When I create a forecast manually in PPDS in transaction RRP3 on the 12.10.2016, I expect to see a dynamic pegging with the stock and forecast element but it doesnt create any pegging relationship between them. Can you please advice if I am missing any configuration?
Thanks,
Rajan.
Hi Rajan,
Usually, having all Shelf Life dates visible in the elements tab will help identify why the stock and forecast are/aren't compatible with each other:
The following conditions must be met for the elements to be peggable:
1) Requirements Date/Time >= Availability Date/Time + Maturity Time - Maximum Lateness of a Receipt
2) Requirements Date/Time + Required Minimum Shelf Life <= Availability Date/Time + Shelf Life
3) Requirements Date/Time + Required Maximum Shelf Life >= Availability Date/Time + Shelf Life
or, in a simplified way:
1) ReqDate/ReqT >= Mat. SL date/time - Maximum Lateness of a Receipt
2) Req. SL Date/Time <= Expiration Date/Time
3) ReqMaxShelfLifeDate/Time >= Expiration Date/Time
Regards,
Tiago
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
12 | |
4 | |
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.