MRP type and purchase requisition date

Hi, is there an existing MRP type to enable the MRP run to generate purchase requistions with a req. date at 1st day of the month, no matter where the demand is ? Thanks

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Sep 06, 2017 at 01:22 PM

    Hello

    Yes, you can use a periodic lot sizing procedure, so that MRP creates a single requisition for all the requirements in the period.

    The standard lot sizing procedure MB is available with a monthly period and if you want a more specific period, you can use lot sizing procedure PK and create your own planning calendar.

    Regards,

    Caetano