MRP type and purchase requisition date

Sep 06, 2017 at 01:20 PM

46

avatar image

Hi, is there an existing MRP type to enable the MRP run to generate purchase requistions with a req. date at 1st day of the month, no matter where the demand is ? Thanks

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Caetano Almeida
Sep 06, 2017 at 01:22 PM
0

Hello

Yes, you can use a periodic lot sizing procedure, so that MRP creates a single requisition for all the requirements in the period.

The standard lot sizing procedure MB is available with a monthly period and if you want a more specific period, you can use lot sizing procedure PK and create your own planning calendar.

Regards,

Caetano