Resource Related Billing
We want to manage a project for fixed price milestone billing along with actual expense elements
Therefore in the contract
One line of fixed price milestone including billing plan
One line of T&M that will be billed from DP91 - linked to DIP profile
Is there anyway to consolidate the fixed price element from the contract into the Debit memo request?
I can produce invoices for both elements and then combine from an invoice list later in the process, but would like to know if anyone had managed to collective alloacte the line items within the original DMR.....