mrp run

hello,

any body please help me. my client requested they need to rum mrp in two times. that is they want to run mrp in head office for three months. and in plant they want rum mrp for one month.why three months means they need to plan short falls of rm and pm and plan. please give me idea on this issue.

bhakta

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Sep 19, 2007 at 03:17 PM

    You can run the program- MD02 ( SAPMM61X) in the background and set it for diffrent intervals with the required parameters.

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Sep 19, 2007 at 04:19 PM

    Use MDBT-MRP in background.

    In IMG

    In MRP setting of the head office the planning horizon should be 100

    In MRP setting of plant the planning horizon shpould be 31 days.

    In MDBT use the followng setting

    Processing key - NETPL

    Creating percase req - 2

    Delivery scedule - 3

    planning mode =1, other settings, you need to decide.

    Please let us know if it helps you

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.