hello,
any body please help me. my client requested they need to rum mrp in two times. that is they want to run mrp in head office for three months. and in plant they want rum mrp for one month.why three months means they need to plan short falls of rm and pm and plan. please give me idea on this issue.
bhakta
Use MDBT-MRP in background.
In IMG
In MRP setting of the head office the planning horizon should be 100
In MRP setting of plant the planning horizon shpould be 31 days.
In MDBT use the followng setting
Processing key - NETPL
Creating percase req - 2
Delivery scedule - 3
planning mode =1, other settings, you need to decide.
Please let us know if it helps you
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You can run the program- MD02 ( SAPMM61X) in the background and set it for diffrent intervals with the required parameters.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.