difference in planning types

Dear sap pp guru's,

can anybody tell me what is th difference between (practical difference)

1) NETCH - net change planning.

2) NETPL - net change planning for total horizon.

3) NEUPL - Regenarative planning.

regards,

Nilesh

Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Sep 19, 2007 at 11:45 AM

    Hi Nilesh,

    NEUPL --- regerative planning -


    Irrespecitve of the planning file entries, all the materisl will be planned , this might take long time as there are no restrictions.

    NETCH --- Net change planning -


    When we select this option, only those materials with planning file entries or in other words with MRP relevant changes are planned , no restictions on the PLanning Horizon, If there is a requirtement after 2 years that is laos planned.

    NETPL---- Net change planning totoal horizon --- Similar to NETCH with the planning done within the Planning horizon.That is if we define 100 days as planning horizon, any requirement out side this 100 days is not planned.

    Reward if the solution is Ok with you.

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Sep 19, 2007 at 11:39 AM

    Hi,

    1.NEUPL - This key is selected normally during initialisation of SAP.

    2. NETCH - This key is used when u want to do planning for all materials that have undergone a change. Here planning is done for the entire period.

    3. NETPL - Similar to NETCH; but planning is done only for the planning time fence.

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Sep 19, 2007 at 11:48 AM

    Hi Nilesh,

    1) NEUPL - This is Regenerative Planning means this is generally used when u r running MRP for the first time or can be used in the later stage in Production if u find some data Inconsistency.In these all the materials are planned irrespective of any changes made to them.As this includes all the materials therefore load on the system increases.

    2) NETCH - This is Net change Planning means it plans the materials which have undergone some changes relevant from MRP since the last planning run.After last MRP runs if u have made any changes like in BOM,Sales order etc the system will consider only that particular materials for Planning.

    3) NETPL - This is Net Change Planning for Total horizon means it will plan only the materials which have undergone changes within the Planning Horizon which u have defined.Therefore It restricts the materials to great extent.

    Hopes this satisfies ur need.

    Reward points if Useful.

    Regards,

    Rakesh Wade

    Message was edited by:

    Rakesh Wade

    Message was edited by:

    Rakesh Wade

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.