CATS time sheet postings against to General Cost Activity in SAP PS

Dear Experts,

My client wants to post CATS postings against to General Cost Activity in SAP PS. For this requirement I have done change as “confirmation mandatory” in control key PS03. System asking work center mandatory while executing CAT2 transaction. Could you please advice me am I miss any configuration settings for this.

Thanks in Advance,

Ramakrishna

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Sep 14, 2017 at 08:09 AM

    Hi Rama,

    Work center is required to post time sheet.

    You can create a dummy work center, then uncheck the cost in the control key so the costing will not be posted. But still system will allow you post the Activity cost through FI

    Regards

    Terence