Dear all,

Is there any way to fix a material not to change in a production order before reading pp master data.

Thanks,

Murat

Accepted Solutions (1)

Accepted Solutions (1)

former_member196398
Active Contributor
0 Kudos

Murat,

Can you please explain what excatly you require?

Regards,

Prasobh

Former Member
0 Kudos

Dear Prasobh,

First, I want to add a material into a production order which is not in the BOM, and then when i read the master data of this production order for the BOM explosion, i don' t want to this added material to be changed or deleted.

Thank you .

Murat

Former Member
0 Kudos

The std SAP functionality usually deletes the additional item if you do a Read PP master data after adding the item. I do not think this is possible with existing features in SAP.

former_member196398
Active Contributor
0 Kudos

Murat,

It is not possible to restrict deletion of manually added components during Read PP Master data.

Regards,

Prasobh