Sub Contract PO - Difference between New PO and Change PO (PORDCR1 ->RON)

Hello There:

We are using Purchase Order Collaboration with Contract Manufacturing.

We create a new PO in ECC. IDOC PORDCR1.PORDCR102 is then transformed to RON.

When we change the PO in ECC it sends out the same IDOC PORDCR1.PORDCR102 and creates RON which is fine.

When we did a difference between these 2 files, only the create date/time and what I changed on the PO is different.

Is there any kind of flag we could set in ECC that would distingiush these same IDOCs for a new PO versus changed PO?

Thanks in Advance

Vivek

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

1 Answer

  • Best Answer
    Posted on Sep 19, 2007 at 04:42 AM

    When the idoc is triggered for the change value, then either it should have a field indicating that it is idoc with updated fields, or u can enhance the idoc by adding an indicator field and send it further. U can find the details abt the idoc in we60

    Regards,

    Prateek

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.