COPA document (profit center valuation view) not matching with material cost estimate.

former_member240927
Discoverer
0 Kudos

We have a scenario where the value in CK13 - Material cost component is not matching with the COPA document posted from the billing document.

The issue is only for profit center view (and not legal view) where it seems the values are picked from previous cost estimate and not the new costing estimate / costing run.

The system used is SAP 4.6c.

Accepted Solutions (1)

Accepted Solutions (1)

former_member240927
Discoverer
0 Kudos

This issue is resolved, the issue was that we had two costing variants and based on the configuration the price based on current period from material master would be picked. The user had mistakenly ran only only only one cost estimate for one costing variant in PC view and this didnt changed the current period price in MM03.

Once user executed the cost estimate for both the legal and profit center view then the issue was resolved for CK13.

Regards

Nikhil Kothari

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Nikhil,

Cost estimate is generally read based on PGI date. please check when was executed your PGI and cost estimate is validate or not on that date.

check KE40 configuration settings for costing keys and compare cost estimate date and PGI date etc.

Thanks,

Rau