Production order settlement variance

Hi all,

New to SAP so apologies in advance.

Problem....when production orders are settled and variances calculated the variance is posted to PA. For out UK entity this has worked but for the US they have not and we have a £3k difference between FI and PA. After investigation, PA is less than the GL and it would appear that it relates to a specific product that is normally made in the UK but has been transferred to the US for finishing.

Can anyone guide me into where to start my investigation.

Thanks in advance.

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

2 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Sep 18, 2007 at 03:42 PM

    I am not sure if i understood the problem right. But please start checking the production order for that product and the settings for PA transfer structure where you will do the settings for transfer of variances.

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Sep 18, 2007 at 04:05 PM

    You may have to start from the production orders in the US environment.

    Check the order type used for finishing the material that arrived from UK. (T-code KOT2 can tell the properties of the order type)

    The order type shall have a settlement profile in its general parameters.

    Going through the SPRO menu Controlling>Product cost controlling>Cost object controlling>product cost by order>Period end closing>settlement>create settlement profile (for viewing/changing the settlement profile)

    Locate the profile concerned and double click. Check if the valid receiver includes Profitability segment as settlement allowed.

    Then ensure the PA transfer structure is included in the profile. The profile is maintained in KEI1. Here you link the type of variances to the value fields.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.