on 09-18-2007 12:52 PM
Hello,
Can any one guide me In SAP B1 Production Module after preparing Production order shall we proceed to <b>Issue for Production</b> or <b>Receipt from Production.</b>
Also when I am preparing Production In screen it needs Product no.----
How can I go furthur.
Regards
P.Narender
hi narender....
actully ur problem is quite confusing
but i think ur problem is related to mannual or backfflush
i also experienced thesame problem but this problem might b a bug
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
When the Production Order type is Standard or Special & issue type is Back Flush, we can proceed with Receipt from Production. Production type is Standard & issue type is Manual we can proceed with Issue for Prodcution.
If Production Order type is Disassembly or Special, receipt from production will be opened.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
It is depend of the type of your Production Order (type.OWOR).
If the Production Order is standard, (Type = A), you need to do a Receipt from production (button Production Order) to get final goods and consume raw materials
If the Production Order is disassembly (Type = D) you need to do an issue for production (button Disassembly Order) to get initial raw materials and dissassemble the final goods
Regards,
Sébastien
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.