Is there a configuration to copy equipment master work center to work order? ( SAP PM)

Oct 12, 2016 at 11:14 AM

54

avatar image

Hello experts,

Is there a configuration to copy equipment master work center to work order? ( SAP PM)

if not is it standard code that does it?

Thanks,

Raneetha

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Peter Atkin Oct 13, 2016 at 11:11 AM
0

Raneetha

It is standard code that copies the main work centre to the order HeaderData tab, and the work centre to the Location tab on the order.

Why do you ask?


PeteA