Dear All

As a month end activity, period close is done and production orders settlement happens and WIP entry posted to GL

Is there is any T.Code in Sap to locate the part no as individual piece part level, WIP qty and amount to match with WIP Gl amount after settlement of production orders

With Regards,

Francis

3 REPLIES 3

Former Member
0 Kudos

Hi,

You can use the T-Code KKAS to get the WIP Qty against a given plant/material combination.

some of the other supporting t-codes are:

KKAO WIP Calc.: Collective Processing

KKAQ Display WIP - Collective Processing

KKAT WIP Display for Product Cost Coll.

KKAV WIP Calculation for Cost Object Hier

KKAW WIP Display Cost Object Hierarchy

KKAX WIP Calculation for Order

KKAY WIP Display for Order

Regards,

JLN

0 Kudos

Hai JLN

Whether this T code KKAS Wip total will match with my Wip Gl for a particular month and also which qty will be WIP qty ie plan or Gr qty

Regards,

Francis

0 Kudos

Hi,

Pls try this our for some part nos/plant combination in quality system or prodcution system. Mostly this should match the WIP qty .

Regards,

JLN