Plese give me the complete information about ASAP metodology?
hi sudhakar,
ASAP (AcceleratedSAP) is a step-by-step methodology for speeding up the implementation of an SAP R/3 system. The components of ASAP, which can be used together or individually, are called accelerators. Accelerators are based on the best practices of SAP customers from around the world and consist of a number of templates, questions, and scenarios that require user input to help the user determine the best way to implement their R/3 system. According to SAP literature, ASAP can reduce the time required to implement an R/3 system by as much as 50%.
ASAP is shipped automatically with every R/3 delivery and upgrade. There is no charge for ASAP.
here is the diffrent division of ASAP...
ASAP METHODOLOGY
Phase 1
<b>Project Preparation -</b> The primary focus of Phase 1 is getting the project started,identifying team members and developing a high-level plan.
Phase 2
<b>Business Blueprint -</b>The primary focus of Phase 2 is to understand the business goals of the company and to determine the business requirements needed to support those goals.
Phase 3
<b>Realization :-</b>
The purpose of this phase is to implement all the business and process
requirements based on the Business Blueprint. You customize the system step by step in two work packages, Baseline and Final configuration.
Phase 4
<b>Final Preparation -</b> The purpose of this phase is to complete testing, end-user training,
system management and cut over activities. Critical open issues are resolved. Upon the successful completion of this phase, you will be ready to run your business in your productive R/3 system.
Phase 5
<b>Go Live and Support -</b> Transition from a project oriented, pre-productive environment to a successful and live productive operation.
For more info have a look.......
http://www.sapfans.com/sapfans/asap/be_01_e.htm
regards
biplab
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Hey are you asking for the Implementation methodology used by SAP-XI.It is known as
AcceleratedSAP (ASAP) Roadmap.
The ASAP Methodology has five phases:
1. Project Preparation project formally initiated and planning well under way.
2. Business Blueprint project team gathers requirements and conducts conceptual design of the solution.
3. Realization system solution is built and integration tested, end users trained
4. Final Preparation final check before cut over to new system solution
5. Go Live & Support solution confirmation, on-going support in place and project closing
The ASAP Implementation Roadmap for Exchange Infrastructure provides guidance for the implementation teams embarking on implementation project of SAP XI Solution.
http://www.sap-basis-abap.com/sapgeneral/what-is-asap.htm
Refer link below for a brief ASAP stages
ASAP SAP IMPLEMENTATION
http://help.sap.com/printdocu/core/Print46c/en/data/pdf/SVASAP/SVASAP.pdf
http://media.sdn.sap.com/html/submitted_docs/Implementation_Roadmap_XI/index.htm
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi sudhakar !
check this link
It has 120mb.
Regards,
Matias
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
90 | |
10 | |
10 | |
10 | |
7 | |
7 | |
6 | |
5 | |
4 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.