Hi All,

I am trying to generate work schedule manually.

I have given all inputs in the coressponding fields as follows.

Employee subgroup grouping: 5

Holiday calendar: aa

Personnel subarea grouping: 55

Work schedule rule: aaws

Calendar month from (mmyyyy): 012007

to (mmyyyy): 122007

Now the error is

"Error while accessing public holiday calendar on 20080101".

Could some one help me. I got struck at this point.

Regards