Our client requirement is to trigger few characteristics after every 5 lots.

Ex. There will be 10 characteristics in plan, for four lots created user maintains results for only 6 characteristics and remaining 4 are optional.

For the fifth lot user maintains results for all 10 characteristics.

Request your inputs/suggestions for addressing this scenario.

Regards

Venkata

Accepted Solutions (1)

Accepted Solutions (1)

former_member42743
Active Contributor

Have you searched for anything yet?

This is pretty much standard SAP. Dynamic modification at the characteristic level. Please search and read the help files on this functionality.

Craig

Answers (1)

Answers (1)

Former Member
0 Kudos

Dear Craig

Thanks a lot for the reply.

Yes have found out it is possible through DMR at the characteristic level and given the solution to client.