Hi
I am using a copy of Std SNP planning book for SNP since I need to add various Z key figures. Safety stock is also manually maintained added in the planning book(in Z key figures). These key figures are time series key figures and hence do not have a order category. How do i ensure that during the Heuristics run, the safety stock added by the planner/caclulted by a macro in a Z key figure is taken into consideration? (in the std SNP planning book, heuristics takes into consideration, stock maintained in the std key figure)
Sandeep