Upgrade 4.6C--> ECC6 , Hardware requirements

Former Member
0 Kudos

Hi Experts,

We are currently in 4.6C R/3 with 46D kernel ( Oracle 9.2DB and HP-UX B.11.00)

We have two servers ( DB instance 12X750MHz 20GB, Application 10X875MHz 20GB) .Machine is rp8400 , disk - 460GB

when we go for ECC6 , I understand we should go for upgraded hardware first. Cananybody please give a high level idea of the new hardware requirements.

Thanks in advance

Arun

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Thanks Nirmal for the response.

It is an Upgrade from 4.6C to ECC .

Could you please let me know where can I get the quick sizer tool

Thanks

Arun

Former Member
0 Kudos

Hello Babu,

kindly go to http://service.sap.com/quicksizer.

You can get the exact hardware size using that.

Thanks & Regards

Vivek

Former Member
0 Kudos

Its it an upgrade to ECC or it will be a fresh installation.

Check with your hardware vendor he will be able to provide you the details.

There are many factors for H/w sizing. You can use the quick sizer tool for details.

Sit with your functional consultant and use the quick sizer tool for a rough estimate

Check the installation / upgarde guide for minimum hardwrae specifications for ECC 6.0

Thanks