Hi gurus,

I am releasing Forecast from DP to SNP for one product-location.

My SNP planning book is in days.

The forecast is 700, we want to have the total forecast in 6 days (aprox 117 per day) from Monday to Saturday.

In order to get this behavior I'm using a TimeStream with only six days assigned to the Shipping Calendar in the Calendar Tab of the Location Master. I got the 117 per day, but I still have demand on Sundays. How can I avoid this?

Thanks in advanced

-Italo

Add a comment
10|10000 characters needed characters exceeded

Related questions

4 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Apr 07, 2008 at 08:47 PM

    Hi Italo,

    In our project, we have exactly the same problem with yours.

    First of all, we are using APO 4.1.

    We have monthly time buckets in DP and I am trying to come up with demands on 6 days a week in SNP. There is no problem about the calculation of the daily forecast quantity. But when I try to release the forecasts to SNP, I still observe demands on Sundays which should not be the case.

    Do you still remember the solution to your problem? I would appreciate any kind of help on this issue.

    Thanks in advance.

    ~isil

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Sep 14, 2007 at 05:44 PM

    I presume you are using the daily bucket profile while releasing the forecasts. Can you specify if Sunday is the day with 117, which day does not have any? Are there any BADIs active during release?

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Sep 16, 2007 at 01:59 PM

    Hello Italo,

    Check as per the SAP Note 414965.

    Regards,

    Chava

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Sep 18, 2007 at 05:25 AM

    In the transaction to maintain the Time streams - /SAPAPO/CALENDAR, in the tab for calculation rule - mark number 1 to 6 (make sure you do not have the number 7 -sunday)

    Then F9 or execute the Caluclate periods icon. Make sure your sundays do not come into play

    Also, in the storage bucket you wouldve used for SNP planning area (more relevant for the time series KF) , make sure this time stream is added. So when you look at your daily data view it should not have any sundays at all

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      if you have some spare Livecache to play with..... i would also suggest having an intermediate DP planning area - configure it with a daily storage bucket with the 6 day Timestream. get the data there and pass it on to the SNP plannign area. (you can restrict the horizon of the transfer)

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.