hi,

I have some problems with automatic assignment in the planning board.

When I push " Automatic Multiday Assignment" the system assigns the order first to the resources with the lower CID, in ascending order (e.g. 25 and then 26 and then 27......).

How I change this automatic assignment strategy ? Are there any criteria?