Skip to Content
avatar image
Former Member

Revenue from Sales Order to Project

Hi,

In Customer Project scenario, I have created a Sales Order and attached to a WBS.

Now in order to flow the Sales order Value (revenue) into the Project, what setting I have to do in IMG.

Please guide me on the same.

Regards,

Deepak Joy

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • avatar image
    Former Member
    Sep 14, 2007 at 05:22 AM

    Hello Deepak,

    The WBS to which you want the revnue postings needs to be a revenue element (operative indicator at WBS to be ticked).

    Just check on the project profile , it should allow revenue postings.

    At IMG, go to the revenue and earnings in Project System.

    Maintain value categories for Revenue planning, Check for integrated planning indicator( for the sales order) for the project profile and maintain revenue cost element.

    Wish you great day ahead.

    Regards

    Vikas

    PS: Reward points if solution was helpful

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Sep 14, 2007 at 01:33 PM

    In Planning profile Tcode-OPSB, at Automatic revenue planning section, flag check box -from sales order and fillup the revenue element in RElem.f.billing plan field.I think it will help u.

    Thanks,

    Sudhir

    Add comment
    10|10000 characters needed characters exceeded

    • hi..

      Are you using billing plans by any chance? if yes, you need to create the billing plan in the sales order so that revenue could be picked up.

      Regards

      Mey

      Note: Reward points if helpful

  • Sep 15, 2007 at 07:46 AM

    Hi,

    Automatic revenue planning can be done through milestone billing.

    Tnx.

    Abdul

    Add comment
    10|10000 characters needed characters exceeded