Hello
I am working on planning scenario for that i have halb material and procurement type as both(In house and external procurement). After MRP run planned order get generated for that halb material. I have option that planned order will convert to production order or PR.
But problem is when i select the detail information of planned order it will show the procurement type as In-house Mfg instead of Both.
I have checked the planned order profile in the SPRO for all planned order profile it showing procurement type only In house and External procurement not both.
So My requirement is when i entered procurement as in house in material master after MRP run it should allow me to convert only planned order to production order even if i maintained purchasing group it will not allow me to convert PR.
So any one can help me