Procurement type

Hello

I am working on planning scenario for that i have halb material and procurement type as both(In house and external procurement). After MRP run planned order get generated for that halb material. I have option that planned order will convert to production order or PR.

But problem is when i select the detail information of planned order it will show the procurement type as In-house Mfg instead of Both.

I have checked the planned order profile in the SPRO for all planned order profile it showing procurement type only In house and External procurement not both.

So My requirement is when i entered procurement as in house in material master after MRP run it should allow me to convert only planned order to production order even if i maintained purchasing group it will not allow me to convert PR.

So any one can help me

Add a comment
10|10000 characters needed characters exceeded

Related questions

5 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Sep 18, 2007 at 02:27 PM

    Vijay,

    I could not understand if you change the material master to "E" after the MRP Run or not.

    Remember that planned orders generated from MRP take this information from MM at the moment of MRP run.

    Please clarify.

    Dario

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Sep 18, 2007 at 02:42 PM

    Hi Vijay,

    MRP settings of material master have precendence over any other level of MRP settings.So if Procurement type is maintained as X in MRP2 view of the materia Master , After MRP the system will allow you either convert to Production order or a Purchase requisition.

    Reward if the solution fits.

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Sep 18, 2007 at 04:22 PM

    Dear Vijay,

    goto the detailed view of planned order, you can see PLAF-SOBES = E or 0

    it cannot be both, hence donot warry about E, F or X, finally what is going to be decided is PLAF-SOBES.

    If it is X, then you will get many push buttons to crete PR and Production order. if not you will get only one.

    see the table - T460P

    you will clearly understand.

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Sep 19, 2007 at 03:01 AM

    Hi,

    First please ensure that in MRP view procurement type is "E" even after it is "E" you are getting option of conversion to "PR" then in SPRO chech the parametre "conversion of planned order" and put radio button onlyfor production order on.

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Sep 20, 2007 at 08:49 AM

    Dear

    Please revert back if not answered, if answered please close the thread

    please don’t keep it open

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.