Hi friends,

I have configured 4 shifts in my workcenters.(A,B,C,G )and their interval with sequences . please suggest me how i can assign these shifts to the capacity data of sheduling in work center . how the system will take these shift wise capacity data in to account for the calculation of capacity availability in case of planning for production order..,?

now i am taking normal available capacity and taking standard available capacity start time from 07:00:00 to end time 07:00:00 .

so please suggest how system will check the capacity available for the order at a certain point of time?