Original Budget change KO22

Former Member
0 Kudos

Hi All,

My problem is I want to maintain the budget Periodically. But in planning profile & Budget profile two options i m getting one overall value & other annual value.

Please tell me where we maintain the setting for maintaining periodic budget values.

Any help will be appreciated.

regards

Meenakshi

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

I think Using KO24 and KO26 u acn change the budget , that is u can supplement or return the budget ( oroginal one)

Try it , pls write back if it works

Anup

Former Member
0 Kudos

Here you can add or deduct the amount from the total amount alloted for the budget.

It is not for changing the budget to periodically

thanx

Former Member
0 Kudos

Hi

You can maintan Budget periodically for cost center by using T code KPZ2

but it is not possible in case of order

Thanks

Ansuman