Hi!
Is it possible to settle the actual costs of PP order to internal order? I don't want to settle the PP order balance to variances, but I need to settle all actual costs to Internal Order.
In the settlement rule I have always Material in the first line.
I changed settlement profile so that also settlement to IO would be possible.
However - I got a warning - that 100% is assigned to material and 100% is assigned to Internal order.
How should I change configuration to make settlement to both Material and IO, possible?
Best wishes,
Karol