Skip to Content
0

No work centers with capacity requirements were found Message no. MD305

Aug 30, 2017 at 08:48 AM

66

avatar image
Former Member

Dear experts,

Please provide solution for above query.

Configuration is like OPJK,PSF,FORMULA ,MRP RUN SCHEDULING 2 is taken,all ticks maintained in work center.Still problem arises

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

3 Answers

avatar image
Former Member Aug 30, 2017 at 10:17 AM
0

Hi Nilesh,

Check for the control key you are using in OP00 if the check box for "Determine capacity requirements" is selected,

also check in OPU3 and OPU5 the check box for "Generate capacity requirements" is selected.

Regards,

Sumit.

Show 1 Share
10 |10000 characters needed characters left characters exceeded
Former Member

Checked all above already found as per required.

Also same happening for another plant also....Please have a solution.

Thanks in advance

0
Caetano Almeida
Aug 30, 2017 at 04:59 PM
0

Hello

Check those documents and make sure that all the settings are correct:

https://archive.sap.com/documents/docs/DOC-52403

https://archive.sap.com/documents/docs/DOC-52397

https://archive.sap.com/documents/docs/DOC-53051

Regards,

Caetano

Show 1 Share
10 |10000 characters needed characters left characters exceeded
Former Member

After all above setting checked but showing same message & when i am maintaining routing for operation time scheduling results it will showing 0 value in your screenshot it will do schedule...any other reason because scheduling not happening will have effect MRP indicator i am maintains lead time scheduling & capacity planning i.e indicator 2 ...Please have expert solution

0
avatar image
Former Member Aug 31, 2017 at 05:05 PM
0

Hi Nilesh,

Have you maintained operation timings (setup / machine / labor) for the operation in routing?

Share
10 |10000 characters needed characters left characters exceeded