Skip to Content

unable to replicate cproject to SAP PS project

Hi experts,

Recently we did PPm 6.1 SP08 upgrade from SP04. While our end to end testing we found that cprojects are not getting transferred to PS.

When we looked into CO cockpit (COCPCPR), we found that cproject is stuck there with the error " error occured during determination of profit center"

I have attached a screen shot of that too.

Please suggest whats wrong here and how to correct this error.

Thanks

Saurabhcproject-replication.png

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Aug 29, 2017 at 04:19 AM

    Hi,

    Any pointers please?

    Thanks.

    Add comment
    10|10000 characters needed characters exceeded

  • Aug 31, 2017 at 09:21 AM

    Dear Saurabh,

    Have you maintained a profit center in the PS-Projectprofile (transaction OPSA)?

    Best regards,

    Judith

    Add comment
    10|10000 characters needed characters exceeded

  • Sep 01, 2017 at 11:38 AM

    Hello Judith,

    We maintained profit center in the PS-Projectprofile (transaction OPSA) and it worked.

    But, before upgrade we dint have any profit center maintained in OPSA and without any issue we were able to replicate PS project in ECC.

    SP08 upgrade guide also dint have this thing mentioned there I think.

    your thoughts please?

    Thanks

    Add comment
    10|10000 characters needed characters exceeded