Hi
In Budget head 8CVLWRKS64 for company code OM64. The entire budget is available . But when we raised service PO, it was aborted due to budget not available. Please give me some suggestions to solve this. And what tcode i need to use for this?
Have you released the budget?
Pa
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
If you r try to raise this po based on internal order - use t.code KO31 to avoid inconsistancy in tables.
If you r try to raise this po based on wbs element - use t.code CJBN to avoid inconsistancy in tables.
In the above t.codes, just u need enter the internal order / wbs element(relevant Project) and execute. Then system will eliminate any consistance in the system.
Sometime back we used these two transaction codes and solved the issue.
Hope it is helpful for u.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
9 | |
8 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.